Risk Management Toolkit

Process Assets

Standard Process

Definitions:
Risk

Risk Management home

Definition's page

Process Assets
Standard Process
  • Definitions
  • Steps of Process
  • Tailoring Guidelines

  • Compliance

  • Self Assessment
  • Compliance Process
  • CMMI Risk Management Goals
  • Risk Review

    Policy

  • AF Policy Directive 90-9: Operational Risk Management, 1 April 2000
  • AFI 90-901: Operational Risk Management, 1 April 2000
  • AFMC Instruction 90-902: Operational Risk Management, Dec 2007

    Support Assets
    Procedures

  • Affinity Diagrams
  • Brainstorming
  • Risk Plotting
  • Risk Statements

    Taxonomies

  • Individual
  • Consolidated
  • Risk Areas

    Tools & Techniques

  • RiskNav
  • Risk Matrix
  • Risk Radar
  • Cost Risk and Uncertainty - Chapter 14, GAO Cost Estimating and Assessment Guide, Mar 09

    Training

  • Risk Process Orientation
  • Detailed Risk Process
  • Facilitator Training

    Examples

  • Sample Risk Management Plan
  • Process Lessons Learned

  •   

    Risk is a measure of a project's inability to achieve system life cycle objectives ... such as the following:

    • Assurance of Program Viability
    • Provision of Operational Capability
    • Delivery Within Negotiated Baseline
    • Assurance of Operational Asset Survival
    • Assurance of Mission Success
    • Assurance of Personnel Safety and Performance
    • Assurance of Integration with Operational Environment

    Risk has two components:

    • the probability (or likelihood) of failing to achieve particular system life cycle objectives
    • the consequences of failing to achieve those objectives.

    Reference: Based on Definition from AFMCP 63-101C



    Back to top